In short
- The new Code on spatial planning, urbanism and construction (Law 169/2026) applies from 25 August 2026 [1][2].
- In Bucharest, zoning plans are approved by the General Council of the Municipality, not by the sectors [5].
- Reported duration in recent years: 12–24 months; the new Code targets about 7.5 months [3][6][7].
- Zoning risk is handled in the contract, through conditions precedent tied to obtaining the plan [8].
When a zoning plan is required
A zoning plan (PUZ) sets, for a defined area, the permitted uses, building heights, site coverage (POT) and floor-area ratio (CUT, the Romanian FAR). In Bucharest, a PUZ is mandatory before building permits for plots larger than 3,000 sq m [6]. The same applies, whatever the size, to sites in areas that the General Urban Plan does not regulate in detail [9].
A previously approved PUZ does not remain valid indefinitely. The approving authority sets its validity; once it expires without the investment having started, the land returns to the general rules and a new plan is needed [4].
Stages of the procedure
In administrative practice to date, a PUZ has gone through the same main stages [10]:
- the urbanism certificate, which states that a PUZ is required and which approvals must be obtained;
- the opportunity approval, confirming that the initiative and the study area are accepted;
- supporting studies: topographic survey, geotechnical study, traffic studies and, where needed, environmental studies;
- approvals from authorities: environment, traffic, utilities, fire safety and, in special zones, defence or public order;
- public consultation, with a notice displayed for 25 days and an information report;
- the chief architect's approval, after review by the technical urban planning committee;
- adoption by council decision.
What the Urban Planning Code changes from August 2026
Law 169/2026 was promulgated on 5 August 2026 and applies from 25 August 2026, without waiting for implementing rules [1][2]. Applications filed by 24 August 2026 continue under the old legislation, zoning plans started earlier stay under the law in force when they began, and approvals already issued remain valid [1][2].
- Tacit approval: if an authority does not answer within the deadline, its approval is deemed granted. Exceptions are the initiation approval, the chief architect's approval and defence, public-order and national-security bodies [1].
- An integrated approvals committee handles outstanding approvals through a simplified procedure [1].
- Partial nullity: if only part of a zoning plan is unlawful, a court may annul that part alone [1].
- Plans are prepared in GIS format and published in the National Urban Planning Geoportal [11].
- From 1 November 2028, Bucharest City Hall takes over the issuing of urbanism certificates and building permits from the sectors [3].
For sites in special-use zones, approvals from defence and public-order bodies remain mandatory: tacit approval does not apply to them [1].
How long it takes
Actual durations have varied widely. Developers' representatives cited about 18 months to approve a PUZ [5], while other accounts mention 12, 18 or 24 months [6]. There have also been periods of deadlock: in 2021 it was reported that since late 2020 no zoning plan had reached the General Council's agenda, despite dozens of favourable opinions from the chief architect [5].
The new Code targets about 7.5 months to approve a PUZ and about 65 days for a building permit [3]. These are stated targets, not measured durations; the first plans filed after 25 August 2026 will show how realistic they are.
The Bucharest context
The capital's General Urban Plan dates from 2000 and is extended periodically [12]. Work on a new plan advanced through supporting studies published in 2025 [13], but in summer 2026 an updated plan did not yet exist [14]. Until it is approved, the PUZ remains the tool that sets the rules for a large plot.
Costs
There is no public reference fee. The cost depends on the area, the complexity of the zone and the number of approvals. The budget covers the planning documentation itself, the topographic survey, the geotechnical study, traffic studies and approval fees. The practical recommendation is a written quote from an urban planning firm before signing a transaction.
How risk is shared between seller and buyer
In land transactions, investors frequently make closing conditional on obtaining the zoning plan or the building permit, through conditions precedent in the preliminary agreement [8][15]. The alternative is a price that reflects the land's current status, with the buyer keeping the value created through zoning.
This material is for information only and is not legal, tax or investment advice.
Sources
Sources consulted on 10 October 2026. Figures marked “calculation” are our own, based on the published figures.
- Noul Cod al Urbanismului a fost promulgat: 3 schimbări care pot încuraja investițiile · Wall-Street.ro, 19.08.2026
- Codul urbanismului explicat: ce se întâmplă cu actele depuse înainte de 25 august · Actual de Cluj, 08.2026
- Codul urbanismului a fost adoptat de Camera Deputaților · Digi24, 29.07.2026
- Legea 350/2001, art. 56 – avizarea și aprobarea documentațiilor de urbanism · legeaz.net, versiune consolidată
- Niciun PUZ din București nu a fost aprobat în mandatul lui Nicușor Dan până acum · Economica.net, 05.07.2021
- Cum se poate rezolva problema autorizațiilor de construcție din București · Revista Biz, 24.03.2022
- Codul urbanismului: termene țintă pentru PUZ și autorizații · Digi24, 29.07.2026
- Impact of Bucharest PUZ suspension on ongoing transactions · CEE Legal Matters, 2021
- Zonele nereglementate prin PUG și obligativitatea PUZ · HotNews, 08.03.2012
- Etapele elaborării și aprobării unui PUZ · Primăria Calafindești (ghid public), 2023
- Geoportalul Național de Urbanism și noile reguli din CATUC · Revista Biz, 28.08.2026
- Ciprian Ciucu despre soluția la haosul urbanistic din Capitală · Newsweek România, 21.11.2025
- Noul PUG al Bucureștiului: studiile de fundamentare publicate · Economedia, 25.04.2025
- Supliment rezidențial 2026: încotro merge Bucureștiul · Ziarul Financiar, 08.07.2026
- Considerations on land acquisition in Romania (office, logistic and industrial parks) · Gruia Dufaut, 28.09.2016